WORK PERFORMED THIS WEEK: Continued underground electrical & plumbing. Continued shipping and staging steel. Continued west half steel erection. Prepped east half of the building pad for slab pour. Placed underslab aggregate on east side. Poured the east half slab. Continued work on west side private drive entrance. Continued underground storm drainage inlet & manhole […]The post Construction Update: January 10, 2019 appeared first on Campbell Clinic Orthopaedics.